Evergreen3 - background and introduction
|
The idea of building a new, fast service between London and Oxford goes back a number of years. It was first mooted when Chiltern Railways took over the franchise in 1996, one driver being to reduce traffic on the already congested M40. It became a formal aspiration as part of the company's second franchise agreement in 2002. and in 2003 a number of options for this service were examined in a report authored by Chiltern Railways for the Department of Transport. After extensive discussion and consideration, these options were narrowed down to those that are being considered as part of the current Evergreen3 project. As its name suggests, Evergreen3 is the latest in a series of service improvements which are being implemented as part of Chiltern's 20 year franchise. It is preceded by Project Evergreen1 which comprised 18 miles of track doubling between Bicester and Aynho, near Banbury, and Evergreen2 which included various measures to improve line speed, extra signalling between London and Bicester and two extra platforms at London Marylebone - a 50% increase in capacity - which were completed in 2006. Evergreen3 will be achieved by constructing a short connecting line just south of Bicester, where Chiltern Railways' London-Birmingham line crosses over the proposed East-West line which will run between Oxford and Milton Keynes. The latter will be upgraded from just east of Bicester Town station to Oxford, including restoring much of the double track that was removed many years ago and installing new signalling and safety systems. Bicester Town and Islip stations will be rebuilt and additional platforms provided at Oxford, whilst a new station will be constructed near Water Eaton to serve Kidlington and North Oxford. New train services Chiltern Railways envisages operating two London-Oxford trains each hour in each direction, throughout the day. All trains will call at Bicester Town and Oxford stations, and the new Parkway station in North Oxford. Most trains will call at High Wycombe, and some will call at Islip. Projected journey times will be around 66 minutes Marylebone to Oxford, 58 minutes Marylebone to Water Eaton, 14 minutes Bicester Town to Oxford and 38 minutes High Wycombe to Oxford. All times and frequencies are subject to change. Project programme and the Transport & Works Act The new works will require an Order under the Transport & Works Act (TWA) which is the standard procedure for giving statutory authority for new rail lines. Chiltern will be submitting an application in autumn 2009. This is likely to be followed by a public inquiry prior to the granting of an Order if the application proves successful. Work to upgrade the existing Chiltern line between London and Bicester does not require TWA authority and this could therefore commence earlier than the Bicester to Oxford leg of the route. The EIA and stakeholder consultation The key project priority prior to submitting the application is to evaluate options within the agreed parameters of the scheme and carry out a full consultation exercise as part of this process. To this end, Chiltern has engaged the environmental consultancy ERM (see below) which is carrying out a full Environmental Impact Assessment (EIA) as required by law and leading a stakeholder engagement programme with statutory consultees and other stakeholder groups and individuals. For its part, the EIA is designed to examine the environmental impact of a number of different options which may or may not be adopted as part of a core design for the scheme. In informing the evaluation of these options, the EIA covers such areas as:
In tandem with the EIA, ERM is also carrying out a stakeholder consultation programme which is designed to allow consultees - eg local councils and nature conservancy groups - to consider and comment on the proposed route and to discuss design options. The primary objectives of the consultation are: To inform and engage communities and stakeholders regarding the development proposals. To obtain the opinions, views and concerns of those stakeholders. To identify issues and impacts that would not otherwise be considered, along with suggestions for mitigation as appropriate. Project benefits The new route will bring a wide variety of benefits, including:
The main works proposed are:
The project will be financed by Chiltern Railways as part of its franchise agreement, and is not dependent on public funds. The East-West Rail Link The route between Bicester and Oxford will also be used for the East-West Rail Link. This project is sponsored by a range of public bodies, including the relevant local authorities, and seeks to reopen the rail link between Oxford, Bletchley/Milton Keynes, and East Anglia. The Chiltern Railways scheme will materially assist in the delivery of the East-West project, and Chiltern has thus established a close working relationship with the East-West Rail Consortium. This ensures that the two projects complement each other, and that Chiltern's design work takes full account of East-West Rail needs. |
![]() Chiltern train awaiting departure
at London Marylebone ![]() The interior of Chiltern’s
Clubman train ![]() Familiar motorway
traffic congestion ![]() Derelict track bed beside
the existing line into Oxford Oxford North junction- the
line to Bicester is on the right The existing BicesterTown station The proposed Water EatonParkway station |






